Nabors Drilling Rig 624 reported Moving On the Painter Et Al on 1/2 with projected spud date of 1/4.

http://sonlite.dnr.state.la.us/sundown/cart_prod/cart_con_wellinfo2...

Views: 1145

Replies to This Discussion

Is this TMS RA SUJ ??

Correct.  Click on the link to see the SONRIS Lite Well File.  The full well name includes the unit designation.

I saw a crew out there right before Christmas ....I heard they were putting down 20 " casing...Does that sound right ?  .........Good to see 2 rigs  right down the road.....

conductor pipe

1. n. [Drilling]

The casing string that is usually put into the well first, particularly on land wells, to prevent the sides of the hole from caving into the wellbore. This casing, sometimes called drive pipe, is generally a short length and is sometimes driven into the ground. Conductor pipe is run because the shallow section of most wells onshore is drilled in unconsolidated sediment or soil rather than consolidated strata typically encountered deeper.

They are really working out here ....It's really lit up.....That Rig is really something to see go together that close to the Hwy.....This is an easy one to take a picture of...I ll try to post something this weekend.....

 

Nabors Drilling Rig 624 reported 1/9 Rigging Up, Projected Spud Date 1/11.

Nabors Drilling Rig 624 reported Spud 1/11, 6 days Drilling Ahead @ 4185', 1/16.

Nabors Drilling Rig 624 reported 13 days Drilling Ahead @ 8885', 1/23.

Nabors Drilling Rig 624 reported 20 days Drilling Ahead @ 11300', 1/30.

Nabors Drilling Rig 624 reported 20 days Drilling Ahead @ 17223', 2/6.

They seem to be making Good time on this one...

 

So far, so good.  Don't jinx 'em Kevin.  LOL!