I had found the documents on line with DNR but beyond that I "remained clueless". Didn't think they were that far along to be in "Production" as they just registered July 2018 with the state. (but what do I know?)
Comment on one document mentions Wildcat Oil Field (I had to look that up teaux!).
(lost me again on the TVD thing and BHL thingee but hey ...)
Looks like you are going to be getting a crash course on oil field lingo.
Once location is built (7-10 days once it starts), getting in a rig and drilling this type of well is a 45 to 60 day operation at least.
But don't expect them to get out there right away - oil field is "hurry up and wait" in many instances.
Completion could take months - and reporting results longer.
TVD = true vertical depth (the distance if you were do straight down)
BHL = bottom hole location (the point the operator is looking to put the total depth of the well when all is done)
The Dec. 28 Weekly Rig Report shows no rigs assigned or spud in Vernon Parish. FTW, the term, "spud", refers to the first day that the drill bit hits the dirt, the commencement of drilling.
386 members
97 members
59 members
399 members
242 members
172 members
455 members
118 members
87 members
10 members
© 2024 Created by Keith Mauck (Site Publisher). Powered by
h2 | h2 | h2 |
---|---|---|
AboutAs exciting as this is, we know that we have a responsibility to do this thing correctly. After all, we want the farm to remain a place where the family can gather for another 80 years and beyond. This site was born out of these desires. Before we started this site, googling "shale' brought up little information. Certainly nothing that was useful as we negotiated a lease. Read More |
Links |
Copyright © 2017 GoHaynesvilleShale.com