Does a permit have to be obtained from the state before a workover can be done on a well?  The well on our property has been off since June.  Chesapeake says a workover is to be done.  What takes so long?

Views: 263

Reply to This

Replies to This Discussion

Carolyn:

A work permit would have to be obtained by an operator if one were to perform a major workover, stimulate the well via acid treatment, hydraulic fracture, plug back, deepen, squeeze old perfs, reperf, recomplete to a different zone, sidetrack, etc. Ordinary well maintenance (clean outs / flushing / resizing chokes not resulting in production greater than the allowable, etc.) does not generally require a permit.

The answer to other question is less precise. Scheduled work overs can be done with relatively short notice, however, if a well goes down unexpectedly, delays on booking a rig which can effect the proper workover can be extended based upon rig availability.

RSS

Support GoHaynesvilleShale.com

Blog Posts

Tuscaloosa Trend Sits On Top Of Poorest Neighbourhood For Decades - Yet No Royalties Ever Paid To The Community -- Why??

In researching the decades-old Tuscaloosa Trend and the immense wealth it has generated for many, I find it deeply troubling that this resource-rich formation runs directly beneath one of the poorest communities in North Baton Rouge—near Southern University, Louisiana—yet neither the university ( that I am aware of)  nor local residents appear to have received any compensation for the minerals extracted from their land.

This area has suffered immense environmental degradation…

Continue

Posted by Char on May 29, 2025 at 14:42

Not a member? Get our email.

Groups



© 2025   Created by Keith Mauck (Site Publisher).   Powered by

Badges  |  Report an Issue  |  Terms of Service