Today, 3/30/19, Southwest Mount Common Field, West Feliciana Parish.

Views: 1700

Replies to This Discussion

It is done at the request of the applicant.  The slant aligns with the preferred axis of the laterals.  Allows the operator to take full advantage of spacing regs.

They drill and frack perpendicular to strike.  When the strike is NW/SE that is what you get.

Jay

Unit is most probably tied to the preferred lateral orientation of the planned laterals in this area. This direction is not necessarily N-S.

Failure to drill laterals in the proper direction negatively impacts fracture stimulation efficiency and well results.

I apologize for the answers that are redundant with what Jay and Skip have just noted - I missed their comments before putting mine out there!

I'd say that about covers it.  LOL!

Thanks Skip!  I see that now.

You're welcome, Lisa

Erwin #1 was 16 days drilling @ 12,462' on Friday, 4/12.

Appears to be drilling pretty fast.

Vertical hole should go quickly barring complications. Things will slow once they start drilling curve and get set up for go horizontal.

Erwin #1 was 23 days drilling ahead @ 12,932' on Friday, 4/19.

Only 470' of progress in past week - have to assume either drilling problems or lots of tripping and changing out BHA to start drilling curve for lateral.

One option good - the other not so good!

Time will tell.