Looks like they got pipe stuck while attempting to set casing in the hole. SONRIS shows more than a few attempts at trying to fish pipe and/or coil tubing out of the hole. Apparently there was enough material pulled out of the wellbore to allow for a sidetrack of the existing radius and lateral; looks like J-W is going to drill the lateral again.
Last report on 2/23 (new report should be posted shortly) is that they have started the lateral at approx. 10162' and drilling. Cross your fingers if you're leased. From this point to frac and flowback is usually 30± days, maybe a little less.