Started moving in Thursday. Worked through weekend.  Have almost got derrick ready to go up on Springhill Church cutoff road between Hwy 154 and Hwy 4.

Views: 158

Replies to This Discussion

My family has 156 acres in this section. We have taken several pics of this rig. Any updates that you have knowledge of would be appreciated. Thanks, Melinda
They've been drilling all week. A second location staked across the road in east cutover of Mary property.
Would that be in the same section? I do not have my sectional map with me at work.
Mary property extends from one side of section 14 to the other. Four 40's in a row. Any well drilled on Mary property will be in section 14.
Any update on status of this well.
05/04/2010 09 16917 WAITING ON COMPLETION according to sonris
Jon,
The well is completed and on line as of 8/18/10. Initial production above 10MMCFD, but choked back to 8 to 8.5 MMCFD immediately by Questar. Bottom hole pressure holding at 8000psig.
Thanks for update
NEW UPDATE 8/31/2010 New well pad being cleared next to Mary 14-H. The pad is in section 23, but is supposed to be a double. Sign is Pedro 23-15-10 1H/14-15-10 1H ..They must have liked what they found at the Mary 14-H. WW