I am confused.....Well #242358 states 18 days of well producing and paid accordingly.  However - the fracking wasn't completed until about August 31st.  Can this be correct? Produces before fracking complete?

Views: 217

Reply to This

Replies to This Discussion

Smith, the well was completed and tested on August 18th at a rate of 7784 Mcf per day.  The well produced 98,426 Mcf during the month of August.  Assuming the well produced for 13 days during the month that would be an average rate of 7571 Mcf per day.

RSS

Support GoHaynesvilleShale.com

Blog Posts

The Lithium Connection to Shale Drilling

Shale drilling and lithium extraction are seemingly distinct activities, but there is a growing connection between the two as the world moves towards cleaner energy solutions. While shale drilling primarily targets…

Continue

Posted by Keith Mauck (Site Publisher) on November 20, 2024 at 12:40

Not a member? Get our email.

Groups



© 2025   Created by Keith Mauck (Site Publisher).   Powered by

Badges  |  Report an Issue  |  Terms of Service