New Welll permitted in Ora Field 4/26

TOM-ROSA CORPORATION 001 A244 7145 56 00 017 22N 01W 04/26/2013

Views: 13336

Replies to This Discussion

SPUD 7/18/13 JUSTISS RIG #56 9 DAYS DRIL @ 317' 7/26

07/29/13: DRILLING AHEAD @ 7483'. This looks like pretty fast progress.

http://sonlite.dnr.state.la.us/sundown/cart_prod/cart_con_wellinfo2...

No comment.  LOL!

Wow 10 days imagine...

8/5/13, DRILLING TO INTERMEDIATED TOTAL DEPTH AT 9650' AND LOGGING.

Don't know what intermediated total depth means, but they are only 750 feet short of their original projected total depth, after only 17 days drilling.

http://sonlite.dnr.state.la.us/sundown/cart_prod/cart_con_wellinfo2...

More no comment.  LOL!

As I understand, There is no extensive coring being done on this well as it was in the Jackson well under previous scrutiny for taking so long to drill. This makes for much quicker drilling with less opportunity for problems. 

How fast a well is drilled in not always the indicator of knowing what they are doing vs. not knowing. It may even be an indicator of how desperate they are to get a hole in the ground.....lol.  

Gatrpaw,

I am just glad someone can drill a vertical hole without mechanical problems. Now they will probably get stuck. My luck!

Judging by info for the Sharp well, it seems that "intermediated total depth" means the depth of the intermediate string of 7 5/8" casing. Below this depth they will probably use 5 1/2" casing to the bottom.

 23 DAYS DRLG @ 9650' 8/9/13

08/12/13: 9650' STUCK IN HOLE. 08/12/13: CAME LOOSE & STARTED OUT OF HOLE.

Surely glad to see it "came loose"!

http://sonlite.dnr.state.la.us/sundown/cart_prod/cart_con_wellinfo2...