Nadel and Gussman Permits SEWARD-GANDY ETAL 20 in 20-19N-7W of Claiborne Parish

http://sonlite.dnr.state.la.us/sundown/cart_prod/cart_con_wellinfo2...

http://ucmwww.dnr.state.la.us/ucmsearch/UCMRedir.aspx?url=http%3a%2...

This is shown as a non-unitized Cotton Valley test and is not listed as a horizontal, but if not why is the permitted depth 14,000 feet. The Cotton Valley should be no deeper than 10000 feet in this area from what I've seen.

Views: 4592

Replies to This Discussion

It's looks like a test well that will drill through the entire CV/LCV interval.  Though permitted to 14,000' there is no guarantee that the well will be drilled that deep.  I think that Nadel and Gussman would like to copy the successful Wildhorse well designs.  That requires finding the right rock.

Thanks, Skip. Also, I see that the top of the Cotton Valley is shown as 10,100 feet in the Waggoner well in Section 9 of T19N R7W, so it is deeper than I had realized.

http://ucmwww.dnr.state.la.us/ucmsearch/UCMRedir.aspx?url=http%3a%2...

To drill through the entirety of the Cotton Valley group can take 1600 or more feet in some locations.

Has the cotton valley ever been drilled horozontial in Claiborne Parish?

I don't think so.  Then again the CV/LCV is a conventional reservoir so the only areas where horizontal wells would be economic would have to be very tight. rock.

Not necessarily. I have seen drilling programs recently for drilling laterals in sands. I sure would like to try that and drill one of theses or a TMS.
Thanks

Where you are seeing those horizontal wells are areas of very low permeability in conventional reservoirs.  Those areas are generally limited in size.

Any specifics on lease offerings for property owners?

The Nadel and Gussman Seward-Gandy et al. 20 is reported rigging up on 10/3/14 with an expected spud date of 10/4/14. The drilling rig will be Nabors #735.

Nabors is drilling ahead at 3350' in the Seward-Gandy et al. 20 as of 10/10/14.

Seward-Gandy et al. 20 was being drilled ahead at 8385' as of 10/17/14.

The Seward-Gandy et al. 20 is drilling ahead at 10565' as of 10/24/14. Pretty fast progress.

RSS

Support GoHaynesvilleShale.com

Blog Posts

The Lithium Connection to Shale Drilling

Shale drilling and lithium extraction are seemingly distinct activities, but there is a growing connection between the two as the world moves towards cleaner energy solutions. While shale drilling primarily targets…

Continue

Posted by Keith Mauck (Site Publisher) on November 20, 2024 at 12:40