Currently there are 102 permitted Haynesville Shale wells in Louisiana that have not yet been spudded. Of these only 74 were permitted by companies that have active drilling programs in Louisiana.
Chesapeake - 27
Shell - 17
Petrohawk (BHP) - 16
Exco - 12
QEP - 2
At least 12 of the above wells are not likely to be drilled leaving 62 undrilled wells in inventory. This is further evidence that the rig count will likely decline further over the next few weeks.
Tags:
There is a difference between an application for alternate unit well locations/spacing and the actual well permit applications for the same wells. Interested Parties receive notice letters for alternate unit well applications, not for the associated well permits. Operators generally apply for the alternate unit well orders with no set schedule to drill them all. The alternate unit orders are effective indefinitely. Well permits are effective only for a relatively short period. Six or twelve months. Unit applications and alternate unit well applications in LA are not well permits.
IR, hearings are different than well drilling applications/permits. It is a step that must occur before drilling permit applications but does not guarantee an operator will actually permit or drill such wells.
My initial posts were concerning actual well permits
While exactly how many alternate unit wells BHP might drill in the near term is interesting, I think more interesting questions (that I don't have time to research right now) are the following:
Across all operators, how many alternate unit well locations are available in the play, assuming 80 acre spacing, and only in sections with productive wells?
Second question, which cannot be answered with any accuracy, is how many alternate unit wells could be drilled with the pads, roads, pipelines, and other infrastructure already in place?
Dbob. there are ~ 11360 unpermitted well locations remaining in the productive Haynesville Shale sections in Lousiana. There would be additional unpermitted well locations in those sections that are also productive in the Bossier Shale.
Pipeline gathering systems and gas treating facilities are generally already in place. Additional well pads and roads would be required.
Les-
Thanks for the info and your comments.
Some of the operators have placed a fair number of their pads to allow for drilling several of the alternate unit wells from the same pad - Its a bit variable based on the local obstacles, and may not hold together in the extended reach lateral development scenario, but I'd hazard a guess that most well pads are capable of supporting at least 2 additional wells, on average, unless they have already been used in an alternate well drilling program or gas factory concept.
Big picture, for someone who might find this thread in the future - although the permit numbers are down right now, and the rig counts are down, there are a huge number of drilling locations, and many of those can be brought on line quickly, provided rigs and completion crews are available.
Dbob, many of the pads were positioned to allow 6-8 wells when the operator has adjacent north-south sections (units). As you said above a pad may support 3-4 wells if used for a single section.
We have a well with Goodrich. Anything there?
Sheri, Goodrich does not currently have any undrilled permitted Haynesville Shale wells.
Thanks . Do they have any new permits?
Sheri, Goodrich has no new well permits.
110 members
386 members
27 members
455 members
440 members
400 members
244 members
149 members
358 members
63 members
© 2024 Created by Keith Mauck (Site Publisher). Powered by
h2 | h2 | h2 |
---|---|---|
AboutAs exciting as this is, we know that we have a responsibility to do this thing correctly. After all, we want the farm to remain a place where the family can gather for another 80 years and beyond. This site was born out of these desires. Before we started this site, googling "shale' brought up little information. Certainly nothing that was useful as we negotiated a lease. Read More |
Links |
Copyright © 2017 GoHaynesvilleShale.com