The Land & Knowles 18 H #1 well is at 15,138 ft. and drilling.


Views: 536

Replies to This Discussion

They are using the same well bore and started sidetracking at 10,645. I understand they have had rig mechanical set backs. Sidetracking may take a little longer also.... I don't know.
Thank you for all your updates, we wouldn't know what was going on otherwise.
Land & Knowles 18 H #1 well update

Tripping out of the hole this afternoon.
Measured Depth: 13,823
Probably another week of drilling before TD.

We waited forever it seems like for the rig to go up, now I can't wait to see it gone. Thanks for the update.
The Land & Knowles 18 H #1 has reached a Total Depth of 16350 and 5" casing has been set and cemented. They should start rigging down Sunday. Let's hope that completion goes more smoothly than drilling.
Finally, yes let's pray everything else goes smooth. Thanks for the update.
FXEF, what's going on with 18-14-14, any news on when they might begin to frac?
Bob and Lisa,

Land & Knowles 18 H #1 update

Coil tubing rig is now prepping well bore for stages to be perforated. Fracturing will take place in a week or two.
FXEF, is there a pipeline in place yet for this rig?
kittycatmama,

Not sure about a pipeline, but tank battery is set up. They probably will run pipeline from the Ben Land well in section 17, just my guess.
FXEF, that is what I figured. Even if they have to lay a pipeline, it won't have to be a long one. The pipeline to Packert wells has gone super fast. It will be interesting to see the test results for Packert Wells
Have you heard what is going on in Sec. 9 of 14/14 on Long Rd. Lots and Lots of pad clearing, construction.
Thanks, you are always a wealth of information FXEF.