Trinidad Drilling Rig 125 reported Spud 9/30, 4 days Drilling Ahead, 10/3.

Views: 1137

Replies to This Discussion

I'll post the update Friday...as usual.

Drilling was completed the week after Thanksgiving.  Fracking should be complete at the end of this week (2/13/15).

Hi John, I was at the well site last weekend. The supervisor said they were moving out this week for the production crew to come in. #2 was at depth and #1 was almost there (on last Sat.). The supervisor kept saying that they are really good wells, whatever that means. They completed both wells in record time. They're still moving forward.

Trinidad Drilling Rig 125 spud the #1 well 11/13 and reported 23 days Drilling Ahead, 12/5.

whats news on this well as of today

RSS

Support GoHaynesvilleShale.com

Blog Posts

History of GoHaynesvilleShale

The History of GoHaynesvilleShale.com

GoHaynesvilleShale.com (GHS) was launched in 2008 during a pivotal moment in the energy industry, when the Haynesville Shale formation—a massive natural gas reserve lying beneath parts of northwest Louisiana, east Texas, and southwest Arkansas—was beginning to attract national attention. The website was the brainchild of Keith Mauck, a landowner and entrepreneur who recognized a pressing need: landowners in the region had little access to…

Continue

Posted by Keith Mauck (Site Publisher) on May 21, 2025 at 6:00

Not a member? Get our email.

Groups



© 2025   Created by Keith Mauck (Site Publisher).   Powered by

Badges  |  Report an Issue  |  Terms of Service