Ensign US Drilling SW Rig 753 reports Rigging Up, 7/18 - Projected spud date 7/19

Views: 647

Replies to This Discussion

Ensign Rig 753 reports spudding the Spears 31-6H #1 7/21, 5 days Drilling Ahead @ 3820', 7/25

Ensign Rig 753 reports 12 days Drilling Ahead @ 8930', 8/1.

Ensign Rig 753 reports 19 days Drilling Ahead @ 11338', 8/8.

Ensign Rig 753 reports 26 days Waiting On Orders @ 11938', 8/15.

Ensign Rig 753 reports 33 days Drilling Ahead @ 15032', 8/22.

Ensign Rig 753 reports 40 days Run Casing @ 19520', 8/29.

  what's the status on the spears 31  on 12/9/14 ?

Initial Production was 1360 BOE/D (1290 BO/420 MCF/D) 15/64 CHOKE, 6210' LATERAL 23 STAGES.

The well will pay mineral owners of record in Section 31 - 2 North, 6 East and the North Half of Section 6 - 1 North, 6 East.  Well plat for Spears 31-6H:

RSS

Support GoHaynesvilleShale.com

Blog Posts

History of GoHaynesvilleShale

The History of GoHaynesvilleShale.com

GoHaynesvilleShale.com (GHS) was launched in 2008 during a pivotal moment in the energy industry, when the Haynesville Shale formation—a massive natural gas reserve lying beneath parts of northwest Louisiana, east Texas, and southwest Arkansas—was beginning to attract national attention. The website was the brainchild of Keith Mauck, a landowner and entrepreneur who recognized a pressing need: landowners in the region had little access to…

Continue

Posted by Keith Mauck (Site Publisher) on May 21, 2025 at 6:00

Not a member? Get our email.

Groups



© 2025   Created by Keith Mauck (Site Publisher).   Powered by

Badges  |  Report an Issue  |  Terms of Service