Trinidad Rig 125 reported Moving On the Bloomer #2H 3/6 with projected spud date of 3/9.

Views: 1501

Replies to This Discussion

Trinidad Rig 125 reported 7days Drilling Ahead, 3/13.

Trinidad Rig 125 reported14days Drilling Ahead, 3/20.

Trinidad Rig 125 reported 21 days Drilling Ahead, 3/27.

Trinidad Rig 125 reported 28 days Drilling Ahead, 4/3.

Trinidad Rig 125 reported 35 days Drilling Ahead, 4/10.

Trinidad Rig 125 reported 42 days Drilling Ahead, 4/17.

Trinidad Rig 125 reported 49 days Drilling Ahead, 4/24.

Trinidad Rig 125 reported 56 days Drilling Ahead, 5/1

Trinidad Rig 125 reported 63 days Drilling Ahead, 5/8

Trinidad Rig 125 reported 70 days Drilling Ahead, 5/15.  The rig is no longer reporting from the Bloomer #2H as of the May 22 weekly rig report.

As of May 29th, I was told by Sanchez an update on the Bloomer #2H well.  It has been dug and the pipe  has been laid horizontally.  They are waiting for the team of  frackers.

Can anyone tell me if they have started?

Thank you!

It should be completed in the next few days if it isn't already.  There is no way to know when Sanchez will announce the well result or file a report with the state.

RSS

Support GoHaynesvilleShale.com

Blog Posts

History of GoHaynesvilleShale

The History of GoHaynesvilleShale.com

GoHaynesvilleShale.com (GHS) was launched in 2008 during a pivotal moment in the energy industry, when the Haynesville Shale formation—a massive natural gas reserve lying beneath parts of northwest Louisiana, east Texas, and southwest Arkansas—was beginning to attract national attention. The website was the brainchild of Keith Mauck, a landowner and entrepreneur who recognized a pressing need: landowners in the region had little access to…

Continue

Posted by Keith Mauck (Site Publisher) on May 21, 2025 at 6:00

Not a member? Get our email.

Groups



© 2025   Created by Keith Mauck (Site Publisher).   Powered by

Badges  |  Report an Issue  |  Terms of Service