Subject: But here is a list of Johnson Trust Wells and approximate drill date.
Johnson Trust 32 (32-12N-13W) Mid-May
Johnson Trust 6 (6-11N-13W) Mid-June
Johnson Trust 29 (29-12N-13W) Mid-June
Johnson Trust 31 (31-12N-13W) Mid-August
Once I have spoken to our pipeline representative I will have a better idea of when the pipeline has/will be laid and when the wells have been frac’ed and ready for production. It generally takes around 60 days to drill these wells. I hope this helps and I’ll get back to you when I have more information. Thanks,
Kevin Manning
Associate Landman-Louisiana
Chesapeake Energy Corporation