Someone previously gave me this info, Tucker #32 #H1 Well, Serial #240406, S32-T17n-R 15W, SPUD 1-1-10. They set it up the first week of January and now it looks like a ghost town. Sound like probably what you are describing.
DM, some Haynesville Shale are now being drilled in 30 days so it is likely the drilling of the well to total depth has been completed. I believe the rig was just recently moved to a well location in the Elm Grove Field in Bossier Parish.
Parkdota, in 2008 the wells were taking almost 90 days. Then in early 2009 the drill time was down to 60 days. Now operators are targeting ~ 42 days spud-to-spud.
Yes, with shorter drill times and lower rig rates the drill cost is down. But, a lot of the savings is being shifted to doing bigger fracture stimulations.
Les, such a large drill time drop amazes me. HBP can now be gained faster hopefully meaning that many people's 2nd wells will come in to play sooner even though years down the road. With drill costs being pushed to bigger fracs I would assume that means bigger production numbers as well. I get the feeling that some of the earlier wells were used almost like test wells to get to this point of shorter drill times, larger fracs, tighter chokes, HA boundry indicators, etc. I'm hoping that saved money for the operators translates to benefits for the royalty owners.