Devon has been drilling since late July...looking for update on status of drilling...rig still on site?? other equipment on site??? we're not local so any info would be appreciated...thanks, Sharon

Views: 125

Replies to This Discussion

I still have not heard much on Bell 1H other than they're drilling... seems like everything out there has slowed way down...
Bill, we were in Center last week. Reportedly, they were 850' from end of drilling depth. Drilling crew was to finish up this past week end and I suppose fracking is next??? Really new to this but suspect we won't hear anything from the company unless it's a division order if we're in the pay. This is our first adventure so we are clueless, but hopefully not shaleless! Thanks for any info you might get. Sharon
Any rumors out there about the Bell? I assume they've completed drilling, any word on the frac?
CE,
We're in the dark about what's going on...no report on file with TRRC as yet, no division orders received but we may not be in the pay...perhaps someone has more info and can bring us up to date.
Sharon, the Bell Gas Unit #1H finished drilling about the end of September. I imagine it is in the queue... waiting on completion. It could still be awhile yet before it is their turn.
Thanks, jffree, always appreciate your knowledge and willingness to share!

Do you have any other information about Bell 1H? Just curious...

Wow.... I guess no news is good news...

We have seven wells that were at or near completion in August/September and then zero, zilch, nada on any of them. I figure some of it has to do with the reduced gas price... but...........?
Bill R,
Were all seven Devon wells or were other operators involved??? I can surely understand the low price reasoning but some info would be helpful...guess it will come in time...We don't have another trip planned to Center but should something come up and we do go there, we can check the site and see if we can get any info to pass on. Thanks...
Bill a lot of this wells are sitting waiting to be completed-- number one delay is waiting for frac crew, water, and pipeline to flow well into after frac. Avg wait I understand is 3-4 months
Adubu, thanks for your input...every little bit of explanation is appreciated. ss
Adubu -
You were right on target with your input, the majority of the wells are waiting either frac crews to be available or for feeder pipes to be hooked up to a pipeline out there. Only one of the companies refuses to give us updates or information. However, one has been listed as, "shut in - unprefed - waiting completion" going on 20 months.

RSS

Support GoHaynesvilleShale.com

Blog Posts

The Lithium Connection to Shale Drilling

Shale drilling and lithium extraction are seemingly distinct activities, but there is a growing connection between the two as the world moves towards cleaner energy solutions. While shale drilling primarily targets…

Continue

Posted by Keith Mauck (Site Publisher) on November 20, 2024 at 12:40