Recent information revealed a 2nd well in Sabine Parish was tested at over 20 MMcfd with a flowing pressure above 8000 psi.  Although the well is now operated by Shell, the completion was executed by their JV partner EnCana.  The previous super well was also in T9N-R11W (Section 20).

 

Shell, Robert Bozeman 29 #H1 Well, Serial #240815, S29-T9N-R11W, Sabine Parish, 20339 Mcfd, 25/64" Choke, 8714 psi Flowing Pressure

Views: 332

Replies to This Discussion

Therese, the rig is currently drilling the Jean Larsen 17 #H1 Well although it may have finished by now.  The surface casing has been set on the remaining five Haynesville Shale wells in this section and are waiting for a drilling rig.

 

Nabors #783 Rig, EnCana, Jean Larsen 17 #H1 Well, SN 242201, S17-T9N-R11W, Spud 4/3/11

Should be flowing by the 1st of August.