The hearing notice I received stated that Encana needed to apply for an exemption to produce the well as they had violated the spacing requirements or something along those lines. I believe the hearing was to be held in late May timeframe. Sonris is still showing as Waiting on Completion for the status (for 2 months now). Scout report says basically the same thing, but also has In Test.
There were two hearing for Bracky Branch field on May 28th, under docket numbers 09-665 & 09-666 (watch out for that one!! its the Devil!!!!)
But seriously, it can take several months for a field order to be issued after a hearing. Follow Bravehearts advice and call if you really need to know.