Brumley 8 in Frac process!
Thanks for the update, Ken. Hope it goes well for you and everyone in S8, T9N-R12W. Sounds like the wells accross the road in section 9 are doing very good.
As well as yours, really solid numbers!
Do yall know anything about Sec 33 t9 12w? I have land there?
Brumley 8 turned to sales Jan. 16.....nothing like having a pipeline in place.
Does anyone know what this well is producing per day. 243365
per Sonnris...15702 mcfd....24/64 choke....Brumley 8
Ken, thanks for the update....and, Congrats on a good well.
Does anyone know if the well # 243106 HA RA SUGG;SAMMO 21-9-12 H, has been fraced or completed? The latest post on Sonris says it is waiting on pipeline. Thanks
Yes, it is noted in the SONRIS Well Scout. 12 frac stages reported on Dec. 29, 2011.