Does a permit have to be obtained from the state before a workover can be done on a well?  The well on our property has been off since June.  Chesapeake says a workover is to be done.  What takes so long?

Views: 263

Reply to This

Replies to This Discussion

Carolyn:

A work permit would have to be obtained by an operator if one were to perform a major workover, stimulate the well via acid treatment, hydraulic fracture, plug back, deepen, squeeze old perfs, reperf, recomplete to a different zone, sidetrack, etc. Ordinary well maintenance (clean outs / flushing / resizing chokes not resulting in production greater than the allowable, etc.) does not generally require a permit.

The answer to other question is less precise. Scheduled work overs can be done with relatively short notice, however, if a well goes down unexpectedly, delays on booking a rig which can effect the proper workover can be extended based upon rig availability.

RSS

Support GoHaynesvilleShale.com

Blog Posts

Tuscaloosa Trend Sits On Top Of Poorest Neighbourhood For Decades - Yet No Royalties Ever Paid To The Community -- Why??

In researching the decades-old Tuscaloosa Trend and the immense wealth it has generated for many, I find it deeply troubling that this resource-rich formation runs directly beneath one of the poorest communities in North Baton Rouge—near…

Continue

Posted by Char on May 29, 2025 at 14:42 — 4 Comments

Not a member? Get our email.



© 2025   Created by Keith Mauck (Site Publisher).   Powered by

Badges  |  Report an Issue  |  Terms of Service