Nabors Drilling Rig 624 spud the 8H #2 9/19. Reported 15 days Drilling Ahead 11,120'.
Nabors Drilling Rig 624 reported 3 days Drilling Ahead @ 5651' on the #1, 10/10.
Nabors Drilling Rig 624 reported 10 days Drilling Ahead @ 11605' on the #1, 10/17.
Nabors Drilling Rig 624 reported 17 days Drilling Ahead @ 11,995' on the #1, 10/24.
Nabors Drilling Rig 624 reported 10/24 Assigned to the #2 with projected spud date of 11/1.
As always, thanks Skip. Is there anyway to understand if they will go back to drilling the #1 at some point in time or do they expect to be finished with it? The depth reported above does not seem like the total desired depth? Sorry for so many questions.
Yes, they will re-enter the #1 at some point. Seems to me that the #1 reported depth would be where the intermediate casing string would be set. I haven't read any statements by TMS operators regarding the advantage of drilling two wells simultaneously and moving back and forth between them. I can't think of any obvious advantage to the strategy from a drilling stand point. If I had to guess I'd say that the advantage may be one of scheduling completion crews and having two wells to frac sequentially in the same location.
Thanks Skip, always appreciate the time and information.
Nabors Drilling Rig 624 reported 24 days Drilling Ahead @ 12,364' on the #1, 10/31.
Nabors Drilling Rig 624 reported 31 days Drilling Ahead @ 15,745' on the #1, 11/7.
Nabors Drilling Rig 624 reported Assigned to the #2 with Projected Spud 11/14, 11/7.
Shale drilling and lithium extraction are seemingly distinct activities, but there is a growing connection between the two as the world moves towards cleaner energy solutions. While shale drilling primarily targets…
ContinuePosted by Keith Mauck (Site Publisher) on November 20, 2024 at 12:40
386 members
27 members
455 members
440 members
400 members
244 members
149 members
358 members
63 members
119 members
© 2024 Created by Keith Mauck (Site Publisher). Powered by
h2 | h2 | h2 |
---|---|---|
AboutAs exciting as this is, we know that we have a responsibility to do this thing correctly. After all, we want the farm to remain a place where the family can gather for another 80 years and beyond. This site was born out of these desires. Before we started this site, googling "shale' brought up little information. Certainly nothing that was useful as we negotiated a lease. Read More |
Links |
Copyright © 2017 GoHaynesvilleShale.com