Does anyone know anything about the completion of these wells. Aethon spud these wells back in September of last year and 8 months later we have not seen anything or heard anything about royalty payments or even received any Division Orders.
Tags:
No G-1 (IP) reports filed and no pending production reported so I'd say they haven't been completed yet.
Not the news you want to hear, but all that Aethon has done on these wells plus the other Hz permits in this same area (total of 13 wells) is to drill surface hole with small rig on about half of them. TD of surface casing around 2600-2700'.
All this work was done last year with the most recent activity in October 2020.
Wating on activity sometimes in the oil field is like watching water boil. Patience is the BIG virtue on things like this.
Shale drilling and lithium extraction are seemingly distinct activities, but there is a growing connection between the two as the world moves towards cleaner energy solutions. While shale drilling primarily targets…
ContinuePosted by Keith Mauck (Site Publisher) on November 20, 2024 at 12:40
97 members
34 members
386 members
27 members
455 members
440 members
400 members
244 members
149 members
358 members
© 2024 Created by Keith Mauck (Site Publisher). Powered by
h2 | h2 | h2 |
---|---|---|
AboutAs exciting as this is, we know that we have a responsibility to do this thing correctly. After all, we want the farm to remain a place where the family can gather for another 80 years and beyond. This site was born out of these desires. Before we started this site, googling "shale' brought up little information. Certainly nothing that was useful as we negotiated a lease. Read More |
Links |
Copyright © 2017 GoHaynesvilleShale.com