I have a few questions to ask about this well if anyone can help. #1 This well site, pad, road to the pad and everything around them was six feet under water for about a week. The rig had already been moved out but the well had not been fraced yet. What was in the pits on site and did it go into Wallace Lake? #2 Last Sunday morning about 28 huge Halliburton trucks went down, I assume to frac the well. Lot's of noise coming from there. How long does it take to frac a well? #3 If Halliburton is doing the frac work for Camterra, why wouldn't their wells be just as good as the bigger players ?
I appreciate all the help we get from the folks on this site. J.J. Jones
1) you'll have to ask Camterra.
2)Typically about a week for a 12 stage frac
3)They have the "potential" to be depending on geographical location. A well in 16/14 is probably not going to be as good as a well in 14/11, just for an example. But Camterra's well in 16/14 has the "potential" to be just as good as Chesapeake's well in 16/14 with Halliburton doing the frac.
You also have to remember those were some of CHK earlier wells prior to the learning curve. I know CHK is currently drilling 4 or 5 wells in that township so it will be interesting to see what the wells will come in at.