East Daley: New Pipelines Could Open Permian Floodgates

Led by the opening of the Matterhorn Express, a slew of projects is set to battle regional bottlenecks in the Permian Basin region but power generation may be the catalyst for newly announced pipelines.

Led by the opening of the Matterhorn Express, a slew of projects is set to battle regional bottlenecks in the Permian Basin region, but power generation may be the catalyst for the pipelines. (Source: Shutterstock.com)

Ajay Bakshani and Maria Paz Urdaneta, East Daley Analytics  Wed, 12/18/2024 - 11:27 AM

Ajay Bakshani is Director of Midstream Equity, East Daley Analytics Maria Paz Urdaneta is Lead Data Analyst, East Daley Analytics

Midstream is back in the Permian Basin. Following the start of Matterhorn Express, investors have pulled the trigger on several new greenfield pipelines to move natural gas away from West Texas. The investments stand to solve a longstanding bottleneck for operators and open the door to more energy production.

________________________________________________________________________

 

The Matterhorn Express Pipeline is a natural gas pipeline that will transport up to 2.5 billion cubic feet of natural gas per day from West Texas to Southeast Texas: 

  • Length: The pipeline will be approximately 490 miles long. 

    Diameter: The pipeline will have a diameter of 42 inches. 

    Origination point: The pipeline will originate in West Texas near Coyanosa. 

    Delivery point: The pipeline will deliver natural gas to Wharton County, Texas at the Coastal Bend Header (CBH). 

    Counties: The pipeline will cross 19 counties in Texas, including Austin, Burnet, Concho, Fort Bend, Glasscock, Irion, Lapasas, Lee, McCulloch, Midland, Reagan, San Saba, Tom Green, Waller, Washington, and Wharton. 

    Developer group: The developer group includes WhiteWater Midstream LLC, EnLink Midstream, LLC, Devon Energy Corp., and MPLX LP. 

    Construction: Construction is expected to begin in June 2023 and conclude by June 2024. 

    In-service date: The pipeline is expected to be in service by the end of 2024. 

  •  

The pipeline will connect to Transco and other pipelines, and will serve domestic consumers including liquefied natural gas export plants on the Gulf Coast. 

 

Views: 20

Reply to This

Support GoHaynesvilleShale.com

Blog Posts

The Lithium Connection to Shale Drilling

Shale drilling and lithium extraction are seemingly distinct activities, but there is a growing connection between the two as the world moves towards cleaner energy solutions. While shale drilling primarily targets…

Continue

Posted by Keith Mauck (Site Publisher) on November 20, 2024 at 12:40

Not a member? Get our email.

Groups



© 2024   Created by Keith Mauck (Site Publisher).   Powered by

Badges  |  Report an Issue  |  Terms of Service