operator spuds well day before lease expires so this extends lease during drilling but now well is TDed rig down and waiting on frac crews to complete well. Lease has typical 90 day clause to extend lease if working on well to result in production. I assume a new 90 day period started at time well TDed and rig moved off site. Operator said they are waiting for frac crew to complete well. What legally can happen if they can not frac well within 90 days to complete and put well to pipe line for production with lease? I don't see how they can pay "shut-in" if well has never produced.