Parker, it appears to me that Petrohawk has more or less adopted Chesapeake's interpretation. The shape of their two most recent map interpretations are very similar.
What a great memory you have, parker! Yes they did, but since that time I have retired and my computer at work got disabled. I can't remember whether I printed it or not, but I'm going to dig aroundand see if I can find it. If I do, I'll share it with you. If not, I'll ask again. I do remember that their response was interesting. One thing I remember them saying was that all of their interpretations are looking more and more alike because they had more and more the same information.
Eight to Ten Wells Per Section. Initially, industry assumed horizontal development based on 60-acre spacing (~10 wells per section) in the Lower Bossier/Haynesville Shale to tap the estimated ~200-245 bcf OGIP and 45-55 bcf of recoverable gas per section. While few well results have been published, it appears as though industry is starting to drift toward 80-acre
spacing (8 wells per section) based on potentially larger effective drainage areas per well. At 80-acre spacing, recoveries would be 5.6-6.9 bcf/well.
This would equate to 18-27% recovery factors, which is low for ultimate recoverable gas in an unconventional shale gas reservoir. Preliminary industry estimates assume 3-5 bcf/well EURs although more recently
Chesapeake has indicated per well EURs could be as high as 6.5-8.5 bcf/well. In our analysis, we have considered a low case estimate of 3 bcf, a base case estimate of 6 bcf, and a high case estimate of 8 bcf. We believe drilling and completion techniques and/or tighter spacing will be required over time to optimize the recovery factor.
Haynesville Shale
Per Well EURs. As we mentioned earlier, preliminary recoverable gas estimates are 45-55 bcf/section. At 80-acre spacing, recoveries would be 5.6-6.9 bcf/well. This would equate to 18-27% recovery factors, which is low for ultimate recoverable gas in an unconventional shale gas reservoir. Preliminary industry estimates assumed 3-5 bcf/well EURs although more recently Chesapeake has indicated per well EURs could be as high as 6.5-8.5 bcf/well. In our analysis, we have considered a low case estimate of 3 bcf, a base case estimate of 6 bcf, and a high case estimate of 8 bcf.