K.R. The well on section 32 is complete and tied in to the pipeline.
Section 31 - Pad was completed almost a month ago. No permit issued yet.
Section 20 - section 20 and section 29 will share a common pad. It's located right on the section line - north half on section 20 and south half on section 29. The pad and new road have been completed for about 2 weeks. Still no permits issued for either section. Rumor has it that they'll drill 20 first and then 29.
CHK has reached TD in Sections 13, 15, 16 and 17. All are waiting on completion, which CHK seems to have no urgency in doing. Also, CHK consistently does NOT file reports with LDNR.