Does anyone know the projected date of this well going online?

Views: 436

Reply to This

Replies to This Discussion

Cindy, it would be helpful to have additional information.  For example, where is the well located, Louisiana: section-township-range?  Texas: survey name and number.  If you have a lease that location description will be in the legal description of the tract of land.  Operator, what company drilled the well?  What parish or county?

API # 419-31740 XTO Energy Well 1HB New Drill Total Depth 21500

Shelby County Texas, Lease name is Murray

Status # 766153

Does that help any

Beats the heck out of just Murray.  LOL!

Cindy, the well is drilled and waiting on completion.

What is involved in completion ?

The lateral still needs to be perforated and frac'd. It will not produce gas until that is done. The well has to be tied into the gathering system (pipeline), as well, and that is usually done before frac'ing. A gathering line has to be extended out to the new well.

How long does that usually take for all that to happen?

They aren't ever in a great hurry but 60 days is about par.

Ok thank you

RSS

Support GoHaynesvilleShale.com

Blog Posts

The Lithium Connection to Shale Drilling

Shale drilling and lithium extraction are seemingly distinct activities, but there is a growing connection between the two as the world moves towards cleaner energy solutions. While shale drilling primarily targets…

Continue

Posted by Keith Mauck (Site Publisher) on November 20, 2024 at 12:40

Not a member? Get our email.

Groups



© 2024   Created by Keith Mauck (Site Publisher).   Powered by

Badges  |  Report an Issue  |  Terms of Service